Earned Value Problem

Write my research paper
1. During a project, Earned Value Analysis is performed and gives the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000.Which results are correct?A. CV: +120,000; SV: +100,000
B. CV: +100,000; SV: +120,000
C. CV: -100,000; SV: -120,000
D. CV: -120,000; SV: -100,0002. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
B. The project’s deliverables have all been finished. The project came in ahead of schedule but on budget.
C. The project’s deliverables have all been finished. The project came in on schedule but over budget.3.You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000.What is right?A. EAC = 550,000
B. EAC = 525,000
C. EAC = 500,000
D. EAC = 425,000Purchase the answer to view it
This is property of essayprince.com. We provide the best Online writing service to our students. Log in today to get access to notch papers

Don't use plagiarized sources. Get Your Custom Essay on
Earned Value Problem
Just from $8/Page
Order Essay
Calculator

Calculate the price of your paper

Total price:$26

Need a better grade?
We've got you covered.

Order your paper
Open chat
1
Hello Good Friend
We are here at your service.
How can we help you today?

Order your paper today and save 16% with the discount code SUMMERFEST020